Clearing that stresses savings on the formwork equipment used. Three days after pouring concrete, 80% of the equipment can be recovered so it can be used on framing an upper slab. The remaining 20% of the equipment is left shoring the poured floor for 21 to 28 days. Accordingly, you can maximize the use of formwork equipment for concrete slabs.